The first visible step was taking things out. Crews began the Downtown Simpsonville Project by removing four concrete islands from Main Street, and the city held its groundbreaking on August 4, as the Greenville Journal reported that week. Since then, most of the work has happened underground. In the city's Committee of the Whole update on October 27, CoTransCo Director of Operations Clay Baldwin reported that Thrift Development's contract, worth about $11.6 million, was 14 percent complete. Crews were working on eight drainage systems before the more visible curb, gutter, sidewalk and roadway work could start.
If you're touring homes near Main Street over the next two years, construction may be part of what you see on a given block, and it's easy to judge a street by that. The construction is the temporary part. The permanent change is easy to miss on a showing. When the work is done, three downtown streets will carry traffic in one direction only, and that pattern will set how a block feels long after the barrels are gone.
The finished downtown is a loop
The City of Simpsonville's project page says that once construction is complete, part of the downtown core will run as a one-way, two-lane system. Curtis Street will run eastbound from Maple Street through downtown to College Street. College Street will run westbound from Curtis back to Maple. Academy Street will run northbound from Curtis to College. Together they form a counter-clockwise loop around the core. East Curtis Street east of College stays two-way and gets a new center turn lane.
The city has published this general pattern since 2022, and SCDOT reviewed the traffic analysis behind it. That review matters because Main Street and Curtis Street include state-maintained routes, where SCDOT controls lane assignments and signals. The city expects that some trips through downtown will mean continuing around the loop instead of turning back, adding about one or two blocks depending on where a driver starts and where they're going. It also says traffic operations will be monitored after the change and adjusted when warranted.
For a buyer, the loop changes the questions to ask about any address on or near these streets. On a one-way street, the traffic past your driveway always comes from the same direction. Your own trip home may now include a lap around the core. Crossing the street on foot may change as well, because the city says a one-way system creates opportunities for shorter pedestrian crossings.
Ten segments, one at a time
The project covers about 2 miles of downtown streets in ten segments, and it won't close the whole area at once. That means the experience of living with it depends on which segment you're near and when its turn comes.
| Segment in the project | What changes when it's finished |
|---|---|
| W. Curtis Street | Eastbound one-way from Maple Street, part of the loop |
| E. Curtis Street | Eastbound one-way to College Street; two-way with a center turn lane east of College |
| W. College Street and E. College Street | Westbound one-way from Curtis to Maple, part of the loop |
| Academy Street | Northbound one-way from Curtis to College, part of the loop |
| NE Main Street and SE Main Street | Rebuilt street, sidewalks, lighting and signals |
| N. Main Street, from W. Curtis to W. College | Rebuilt street, sidewalks, lighting and signals |
| Jonesville Road | Rebuilt street, sidewalks, lighting and signals |
| Hedge Street, from E. Curtis to E. College | Rebuilt street, sidewalks, lighting and signals |
Every segment gets the same underlying package: replacement drainage, utility relocation and undergrounding, a rebuilt roadbed and new pavement, sidewalks, curbs, accessible ramps, landscaping, street lighting and traffic signal improvements.
Phase 1 is College Street and Poinsettia Drive. The city expected eastbound College Street to close before the end of the year, and it has said additions involving Hedge Street and North Main Street were pending pricing. If you're looking at a home near College or Poinsettia right now, you're looking at the block where the work is happening first.
The clock a buyer is actually buying
The city calls this "at least 24 months" of construction that began in August 2026. Its FAQ puts substantial completion of the primary streetscape improvements at August 2028 and says portions of North Main and South Main may take longer, depending on final scope. If you close on a house near downtown this winter, you'll have roughly a year and a half of active construction on the calendar before that August 2028 target.
The city is direct about what that period involves. Its project page answers the question of whether construction will affect your commute or daily activities with "Most likely," and lists temporary lane closures, road closures, sidewalk closures, parking changes and detours at various points. The city expects downtown businesses to stay open throughout, with access to parking, sidewalks and driveways shifting as work moves from one area to the next. Parking changes during construction, and the finished project permanently changes parts of the downtown parking and street network.
The anchors of this rebuild are already in place. City Park and the municipal campus are complete and open. They were built as separate sites, while the streets connecting them stayed largely in their old condition, and those connecting streets are what this project rebuilds. The finished park is already open to the public, and the streets around it are the part still in progress. For what's happening at the park this season, see our guide to Simpsonville's holiday season at City Park.
Private plans are running on a similar timeline. In July 2025, City Council voted to sell the former City Hall at 118 N. Main Street to Blue Ridge Holdings for $840,000 for a mixed-use redevelopment. According to the Post and Courier, initial plans included residential space, retail and more than 200 parking spaces, with completion targeted for June 2028. That target falls within a couple of months of the street work's expected finish.
What Greer's rebuild looked like from the middle
The closest local example is a few exits up I-85. Greer broke ground on its CenterG streetscape in January 2019, after utility upgrades that started in 2017, and it planned for 18 months of construction. When the project began, the city administrator put downtown occupancy at 95 percent, and the city budgeted $150,000 for merchant façade incentives, as GreenvilleOnline reported in July 2019.
Some of Greer's openings came while the street was still torn up. The Upstate Business Journal covered SELECT, Ira's Chicken and L'Incanto opening near Trade Street as construction got underway in early 2019. An owner of Ira's told the paper business was steady through rainy opening weeks and that the 18-month project didn't deter him.
When Phase 1 wrapped up in July 2020, Greer CPW relayed the city's estimate that returns on the project had already passed $100 million in renovated properties and new commercial and residential projects. The same announcement introduced ParkView Greer, a planned $32 million mixed-use project with 226 apartments and a brewery and restaurant. That $100 million figure is the city's own estimate, not an independent study, and it says nothing about home values. It does show the order things happened in. In Greer, businesses committed to Trade Street during construction instead of waiting for the ribbon cutting. If you want to see that finished downtown today, our post on Greer's new art on Trade Street walks the blocks.
Simpsonville's timeline is longer, at 24 months or more against Greer's 18, and the city says the schedule may shift with weather, utility coordination and final scope. A Simpsonville buyer lives with the disruption for longer. In both towns, though, the inconvenience falls on whoever is there during construction, and the finished streets are there for everyone after.
Questions buyers are asking about downtown Simpsonville
How do I keep up with which street is closed? The city runs a text alert line. Text DowntownSVL to 38276 for construction updates and traffic changes.
Why did construction take until 2026 to start? The City of Simpsonville and the Greenville Legislative Delegation Transportation Commission agreed to move forward in 2021. The years since went to engineering design, funding, permitting, utility work, and coordination with SCDOT and the railroad. CoTransCo is the commission's design and management firm, and Thrift Development is the general contractor.
Does the one-way loop apply to all of downtown? No. The city says it applies only to the core, made up of Curtis Street from Maple to College, College Street from Curtis to Maple, and Academy Street. East Curtis beyond College stays two-way.
If a house near Main Street is on your list, a winter showing tells you how the block looks today. The loop map tells you how it will work after August 2028. If you'd like to look at a specific address against the loop map and the construction phases, Book a Consultation with Brockelman Realty and bring the listing. You can also browse our Simpsonville neighborhood page before we meet.